Vetting SIRE 2.0 & PSC // 3rd Officer (Safety Officer) Duties
What a 3rd Officer Must Check Before an Inspection (SIRE 2.0, CDI & PSC): Complete Field Checklist
Ship vetting (SIRE 2.0, CDI, RightShip) is a comprehensive risk assessment of a vessel’s structural integrity, safety equipment readiness, and crew competence that enables charterers and oil majors to select the safest tonnage for their cargoes. Alongside Port State Control (PSC) and Flag State audits, vetting represents the ultimate operational test for shipboard officers. The days leading up to an inspection place immense pressure on the 3rd Officer (Safety Officer), who is directly responsible for Life-Saving Appliances (LSA), Fire-Fighting Appliances (FFA), pollution response gear (SOPEP), and statutory safety records. Below is an exhaustive, field-proven checklist illustrated with real shipboard inspection points and top auditor questions.
Unlike legacy VIQ 7 inspections, SIRE 2.0 vetting evaluates every safety item across three distinct dimensions: Hardware (physical condition and immediate readiness), Process (SMS procedures and PMS maintenance records), and Human Factors (demonstrated crew competence without prompting).
Section 1. SMS Documentation, Crew Familiarisation & Emergency Drills
Inspections almost always begin with a thorough audit of safety files and logbooks. Any discrepancy in paperwork immediately prompts the inspector to scrutinize deck equipment twice as strictly.
Ensure signed Safety & Security Familiarisation Checklists are on file for every crew member. Under SOLAS regulations, basic familiarisation—covering muster stations, emergency exits, lifejackets, and assigned duties—must be completed prior to sailing (within 24 hours of joining the vessel). Copies must be transmitted to the shore office (DPA), and equipment-specific familiarisation (including lifting appliances) must be logged accurately.
Cross-check every posted Muster List (bridge, CCR, messrooms, and accommodation alleyways) against the current Crew List—names, ranks, and cabin numbers must match down to the last letter. Verify that the Annual Drill Matrix is displayed and that watchkeepers exempted from a drill (e.g., gangway or engine watch) are rotated so every crew member participates across all emergency scenarios.
Every Fire Drill report and Deck Log Book entry must explicitly record:
- Alarm activation time, Muster Station headcount report, simulated fire scenario, and briefing of duties;
- Starting of emergency and main fire pumps, charging the fire main, and boundary cooling of adjacent bulkheads;
- Turnout time of the Fire Party donning full fireman’s outfits and SCBA sets (typically under 3–5 minutes);
- Testing of intrinsically safe UHF communications between the Bridge, On-Scene Commander, and Fire Teams;
- Closure of fire doors and fire dampers, isolation of ventilation/fuel, and staging of stretchers and medical first-aid gear;
- Escalation discussion covering inability to contain the fire and transition to Abandon Ship, plus instruction on liferaft operation and portable fire extinguisher types.
Under SOLAS Regulations III/35 and II-2/15, ship-specific LSA Training Manuals and Fire Safety Operational Booklets must be placed on the bridge, in the CCR, and in every crew messroom/recreation room in the working language of the crew. Verify that generic pages describing equipment not fitted on your vessel have been removed and that crew familiarisation signatures are recorded.
- LSA Training Manual: Donning lifejackets and immersion suits, boarding/launching/releasing survival craft, lifeboat engine starting, cold water hypothermia protection, and helicopter rescue procedures;
- Fire Fighting Manual: Safe practices regarding smoking, electrical hazards, and flammable liquids; manual call point operation; fixed fire-extinguishing systems (FSS Code); fire doors/dampers; escape routes; and chemical/cargo fire procedures.
Organize all valid shore servicing certificates for liferafts, Hydrostatic Release Units (HRUs), lifeboats and launching appliances (annual and 5-yearly inspections under IMO Resolution MSC.402(96)), portable extinguishers, fixed CO2/foam systems, SCBA sets, and immersion suits. Ensure all weekly and monthly PMS jobs are closed out on schedule.
Physically verify expiry dates against your master tracking spreadsheet for all pyrotechnics (parachute rockets, hand flares, buoyant smoke), Line Throwing Apparatus (LTA), HRUs, EPIRB and SART batteries, MOB lifebuoy markers, lifejacket lights, medical chest items, and lifeboat food/water rations.
Section 2. Fire-Fighting Appliances (FFA) & Fire Control Plans
Permanently exhibited Fire Control Plans must comply with IMO Resolution A.952(23) / A.654(16) and reflect exact onboard equipment locations. Inspect both port and starboard external Fire Plan Containers (Fire Wallets) near the gangways: enclosures must be weather-tight with free-turning wing nuts, containing (1) an up-to-date Fire Control Plan, (2) a current Crew List, and (3) current cargo MSDS/SDS sheets and dangerous goods stowage plans.
Verify that all IMO symbols across the deck, accommodation, and engine room are clean, intact, and photoluminescent. A common vetting observation is using a generic lifebuoy sticker instead of the exact IMO symbol matching that lifebuoy’s specific attachment (line, self-igniting light, or MOB light-and-smoke signal).
All fire main isolation valves (especially the main engine room/deck isolation valve) must be clearly labeled with open/shut direction plates, greased on the spindles, and fully operable by hand without requiring wheel keys or spanners. Exercise them weekly!
Confirm that the International Shore Connection is stowed at a clearly marked, accessible location near the gangway/fire station, complete with the standard flange, 4 bolts (16 mm diameter, 50 mm length), 4 nuts, 8 washers, an oil-resistant gasket, and 2 spanners.
Inspect sprinkler nozzles inside the Paint Room to ensure none are painted over or obstructed by paint drums, confirm the control valve is properly set/sealed per system design, and check that maximum stowage height lines are stenciled clearly on the bulkheads.
Audit every extinguisher against the Fire Control Plan: check for dents or base corrosion, intact safety pins and seals, pressure gauge needles squarely in the green zone, updated monthly inspection tags, and valid 10-yearly hydro-test markings (IMO Resolution A.951(23)). Verify legible manufacturer plates (extinguishing medium, charge weight, operating temperature range, and pictographic operating instructions) as well as spare charges/extinguishers (100% for the first 10 units and 50% for the remainder).
Inspect every Fireman’s Outfit locker: protective suit, boots, gloves, rigid helmet with visor, explosion-proof (Ex) safety lamp with fresh batteries, insulated fire axe, safety belt, and 30 m fireproof lifeline with snap-hook.
- SCBA Sets (minimum 1,200 L air / 30 min): Cylinder pressure at least 90% of full charge (200 or 300 bar); low-pressure warning whistle tested and sounding reliably at 50–60 bar; facepiece airtightness verified; 1–2 spare charged cylinders per set; valid annual inspection and cylinder hydro-test dates. On chemical/gas tankers, clearly label the 4 FFA sets separately from the 3 additional IBC/IGC Code chemical protective sets;
- Emergency Escape Breathing Devices (EEBD / ELSA): Pressure gauge needle in the green zone, intact anti-tamper seal, stowed per Fire Plan (plus at least 1 clearly marked TRAINING ONLY unit).
Walk every accommodation stairway and alleyway: no self-closing fire door may ever be wedged or hooked open! Door closers must latch firmly without assistance. Inside hydrant boxes, verify neatly coiled hoses, intact coupling rubber washers, dual-purpose Jet/Spray nozzles, hydrant blank caps with zero leaks, and current hose pressure-test records.
Section 3. Lifeboats, Liferafts, Lifebuoys, Lifejackets & Pyrotechnics (LSA)
Ensure the hull is clean and free of cracks or osmosis, with retro-reflective tapes and vessel name/port of registry clearly painted on the bow and canopy. Inside, verify all mandatory LSA Code inventory is properly lashed, rations and water are in date, compressed air cylinders (on tankers/chemical carriers) are 100% charged, and the water spray system, searchlight, internal lighting, compass, and rudder steering operate smoothly.
- Engine Starting: The lifeboat engine must start promptly on each of the two independent battery banks individually (Battery 1 and Battery 2), and the 42V trickle charger must maintain both banks;
- Operating Instructions: Engine starting and On-Load / Off-Load hook release placards must be posted and illuminated under emergency lighting;
- Hatches & Propulsion: Hatch rubber gaskets unpainted, dogs greased, and propeller/rudder clean and well-coated.
Check that container drain holes face downward, capacity and next service dates are clearly stenciled, the ID container is secured, embarkation lighting illuminates the overside water surface, and the Embarkation Ladder is properly shackled to certified deck padeyes with clean, uncracked wooden steps and manropes.
Inspector Hot-Spot (Frequent PSC/SIRE Deficiency!): The liferaft painter line must be attached solely to the HRU Weak Link, and the HRU secured to the deck strongpoint. If the painter is tied directly to the cradle or senhouse slip, the liferaft will sink with the vessel instead of floating free!
Launching posters for lifeboats and liferafts must be mounted right at the operating controls and verified at night under emergency lighting alone—inspectors frequently switch off normal deck lighting to verify readability during blackout conditions.
Confirm 100% crew coverage plus additional suits at remote watch stations (forecastle, engine room, bridge). Zippers must be lubricated with paraffin/silicone and tested for smooth operation, seams inspected for delamination, and whistles and valid lights attached. Shore air-pressure seam testing is mandatory every 3 years (and every 2 years for suits over 10 years old).
On both bridge wings, inspect the Man Overboard (MOB) light-and-smoke buoys: ensure each buoy weighs at least 4 kg to deploy the lifebuoy cleanly from its quick-release chute, check safety pins, and verify expiry dates. On tankers, gas carriers, and chemical tankers, all self-igniting lights on lifebuoys and lifejackets must bear Ex / Intrinsically Safe certification!
Confirm that extra lifejackets are stowed on the bridge, in the Engine Control Room (ECR), and forward (where distance from accommodation exceeds 100 m), with every lifejacket light tested via its push-button switch.
Verify that the bridge watertight locker holds at least 12 rocket parachute flares and 4 Line Throwing Apparatus (LTA) units with valid rockets and igniters, and that the illustrated Life-Saving Signals Table (SOLAS Reg. V/29) is posted on the bridge bulkhead.
Section 4. Specialised PPE, Hospital & Oil Pollution Gear (SOPEP)
Check dedicated PPE stations in the Battery Room, Paint Locker, Cargo Sample Locker, and deck manifold stations: acid-resistant aprons, chemical gauntlets, full-face visors, and in-date sterile eye-wash bottles.
Open the deck SOPEP / SMPEP locker and count every item against the approved inventory list: absorbent pads and booms, sawdust/absorbent granules, non-sparking shovels and scoops, oil-resistant boots and suits, disposal bags, and the portable air-operated diaphragm pump (Wilden Pump) with suction/discharge hoses and bonding wire. Test the pump with deck compressed air and verify suction vacuum prior to inspection!
In the ship’s hospital, verify the Medical Chest Certificate validity, check for expired medications, confirm the Oxygen Resuscitator cylinder is full, and ensure the IMO Medical First Aid Guide (MFAG) is on hand. On the bridge, verify monthly test logs for EPIRB, SART, and GMDSS reserve batteries.
3rd Officer Quick-Reference: SOLAS LSA & FFA Inspection Intervals
| Interval | Equipment & Inspection Scope | Required Log / Record |
|---|---|---|
| Weekly | Visual check of survival craft, rescue boats, and launching appliances; run lifeboat engines ahead and astern (min. 3 min); test General Emergency Alarm; exercise fire main isolation valves. | Deck Log Book & PMS |
| Monthly | Full lifeboat inventory check; inspect portable extinguishers, fire stations, hydrants, SCBA sets, and EEBDs; inspect immersion suits; test EPIRB, SART, and GMDSS survival craft VHF radios. | Deck Log Book, GMDSS Log & PMS |
| Quarterly (Every 3 Months) | Lower lifeboats into the water and maneuver (Free-Fall lifeboats lowered every 6 months with simulated launch every 3 months). | Deck Log Book & Drill Report |
| Annually | Shore servicing of liferafts, HRUs, lifeboats/davits (MSC.402(96)), fire extinguishers, SCBA sets, fixed fire-fighting systems, EPIRB shore-based maintenance (SBM), and Medical Chest. | Shore Service Certificates |
| 5-Yearly | Dynamic 1.1x winch brake load tests and on-load release gear overhaul; hydrostatic pressure testing of SCBA cylinders and foam/CO2 extinguishers (10-yearly). | Class / Shore Certificates |
Top 5 Inspector Questions (SIRE 2.0, CDI & PSC) for the 3rd Officer
During SIRE 2.0 inspections, vetting auditors routinely conduct one-on-one practical interviews with the 3rd Officer beside the lifeboat and fire station:
Walk the entire inspection route with a flashlight and notepad 24 hours before the vetting or PSC inspector boards. Check the small details that trigger easy observations: spare batteries in fireman’s lamps, rubber gaskets inside fire hose couplings, hydrant blank caps, lifeboat flare expiry dates, and unobstructed escape trunks. Stay organized every day with our 3rd Officer Handover Checklist and Top 10 ECDIS Questions in PSC Inspections.
Frequently Asked Questions on Pre-Inspection Preparation (FAQ)